Intervention: injections of KERASTABLE® type HDR® high-density resins (Expanding Polymers) with free diffusion and subsequent installation of 35 MP60 steel micropiles (CE marked product – EN 1090-1:2009)
Depth reached by the micropiles with respect to the foundation laying surface: from 14 to 18 meters.
Driving pressure: from 200 to 220 corresponding to 20/22 tons for each driven micropile.
Duration of consolidation work: 4 working days.
Number of operators used for the work: 3 specialized operators.