Industrial shed located in Viganò (LC)

Consolidation of industrial flooring
Type of building: Industrial shed.
Problem identified: Differential floor subsidence with consequent problems of logistical nature that burden the regular execution of work activities.
Technologies used: injections of high-density KERASTABLE® type HDR® resins (Expanding Polymers) and subsequent installation LIFT PILE®, MP60 steel micropiles (Product CE marked according to European standard EN1090-1:2009) pre-tensioned (European Patent nr.2918731B1) with special “jackets” for driving on the new foundation.
Il Progetto

Extent of intervention:
740 sq. m. using 127 jacketed MP60s and about 400 ILDs (free-spread injections)
Results obtained:
Consolidation obtained
Time of execution: Total duration of 22 working days.