Intervention: consolidation of the seabed by laying 23 Lift Pile® consolidation – MP60 steel micropiles (CE marked product – EN 1090-1:2009) pre-tensioned (European patent no. 2918731) with special jackets for infixing on the foundation and laying of 62 MP60 steel micropiles (CE marked product – EN 1090-1:2009)
Depth reached by the micropiles with respect to the foundation laying surface: from 15 to 20 meters.
Driving pressure: 220 and 230 bar corresponding to 22 and 23 tons per driven micropile.
Duration of consolidation work: 10 working days.
Number of operators used for the work: 3 specialized operators.