Intervention: installation of 54 MP60 steel micropiles (CE-marked product – EN 1090-1:2009) and number 17 Lift Pile® consolidation – MP60 steel micropiles with special jackets on new foundation to be built.
Depth reached by the micropiles with respect to the foundation laying surface: from 5 to 7 meters.
Driving pressure: 220 bar corresponding to 22 tons per driven micropile.
Duration of consolidation work: 10 working days.
Number of operators used for the work: 3 specialized operators.
Fai la differenza con noi
FOLLOW US
Via dell’Artigianato 11, 37021
Bosco Chiesanuova (VR)
novatek@novatek.it
Tel. 045 6780224
Fax. 045 6782021
VAT and Tax Code: 02714870231
SdI: M5UXCR1
Share capital: 3,000,000 euros
REA registration no. 257059