Residential Condominium located in Bologna – Sesto San Giovanni (BO)

Consolidation of foundations with active micropiles by mechanical and patented preloading of the micropile itself
Problem identified: Differential subsidence of the building resulting in masonry cracks.
Technologies used: LIFT PILE®, MP60 steel micropiles (Product CE marked according to European Standard EN1090-1:2009) pre-tensioned (European Patent nr.2918731B1) with special “jackets” for driving on the existing foundation.
Il Progetto

Extent of intervention:
Entire building with 350 MP60
Achievements:
Consolidation achieved and secured
Lead time:
Total duration of 21 working days.
Customer benefits:
Quick and minimally invasive intervention. No inconvenience to the pedestrian walkability of residents.