Extent of intervention:
132 micropiles executed
Results obtained:
Lifting performed: Controlled lifting of 3.5 cm.
Stability achieved: lifting of the structure with partial closure of cracks, restoration of the structure to serviceability.
Time of execution: Total duration of twenty working days.
Customer benefits:
Rapid and minimally invasive intervention.
Any peculiarities:
Final solution of the subsidence problem, with restoration of the structure’s serviceability.
Practical example:
“Intervention in Duisburg on an apartment building garage subject to differential subsidence and presence of numerous cracks. Building declared with “imminent danger.” We performed foundation consolidation using LIFT PILE and a 3.5 cm controlled lift, allowing partial closure of the cracks. The intervention restored structural stability and secured the building, restoring the original market value of the building.
Fai la differenza con noi
FOLLOW US
Via dell’Artigianato 11, 37021
Bosco Chiesanuova (VR)
novatek@novatek.it
Tel. 045 6780224
Fax. 045 6782021
VAT and Tax Code: 02714870231
SdI: M5UXCR1
Share capital: 3,000,000 euros
REA registration no. 257059